London Aquatic Centre, United Kingdom

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Location
Stratford, London, England
Estimated Cost
£240m
Design
Zaha Hadid Architects
Pool Architects
S&P Architects
Contractor
Balfour Beatty
Structural Engineer
Ove Arup
Construction Began
July 2008

The London Aquatic Centre, currently being constructed in the London Olympic Park, is a speciality facility that will host athletics during the 2012 Olympic Games.

The centre has two 50m swimming pools and a 25m diving pool. It will host events such as swimming, diving, synchronised swimming and some of the modern pentathlon. It is being built to accommodate approximately 17,500 people during the Olympic Games.

The aquatic centre was designed by Pritzker Prize-winning architect Zaha Hadid. Construction will be supervised by the Olympic Delivery Authority. The centre will be built by Balfour Beatty, the chief contractor, as well as Ove Arup and pool architects S&P.

The centre was originally estimated to cost £75m, however this has risen to £242m due to inflation and VAT.

Plans to let-out the stadium for public use after the Olympic Games have also contributed to the rise in costs. In spite of the increase, the cost of the centre will still be within the construction budget of £6.09bn.

Zaha Hadid aquatic centre design

The original design of the centre was submitted to the London Development Agency in December 2005. It was later modified as the designed building was too large for the space allocated and also exceeded the budgeted costs. The final design was revised and submitted in November 2006.

"The London Aquatic Centre will host athletics during the 2012 Olympic Games."

The roof of the centre has been designed in a sinuous S-shape, inspired by the flow of water, and signifies a continuation of the Lower Lea Valley landscape.

The roof design, resembling a manta ray, has already been acclaimed as a sculptural masterpiece and is anticipated to become a new landmark in London.

Spanning 11,000m², the column-free roof is 100m high, weighs 2,800t, and is cast of steel and covered by aluminium. It measures 160m in length and 80m at its widest point.

The roof has three supports made of concrete - two cores at the north end and a wall at the south. The two principal trusses sit on these supports. Fan trusses of 115m are located at 9m centres between the two primary trusses. The trusses are cantilevered 30m from the northern cores.

In the east and west of the structure, the roof overhangs by 27m. These overhangs are two inclined arches, which are a part of the roof structure, and run between the northern cores to the southern wall. Both arches are joined at the centre and supported by central fan trusses. The roof has obtained its undulating shape due to the use of arches.

Walkways and other facilities, not visible from the main pool space, could be constructed in the huge depth in order to utilise the space.

"The aquatic centre has two 50m swimming pools and a 25m diving pool."

The centre will have a capacity of 2,500 spectators. Two temporary stands will be built on either side of the centre to accommodate 15,000 people during the Olympic Games.

There will be two platforms in each wing. The first platform will house facilities for the London Organising Committee of the Olympic Games (LOCOG), and the second platform will be for public seating.

Excluding the steel roof, the rest of the structure is made of concrete. Timber will clad the bulbous sides and the ceiling lining of the centre, while aluminium will be used to top off the structure.

Aquatic centre construction

The construction firm Balfour Beatty won the construction contract, which opened for bidding in March 2007. Construction commenced two months ahead of schedule on 17 July 2008, and completion is due in 2011.

"The roof design is anticipated to become a new landmark in London."

Balfour Beatty is constructing the aquatic centre as well as a huge land bridge. The land bridge, which acts as the training pool roof, is also the main access to the Olympic Park for pedestrians. It will cost £61m.

The river running beside the structure has been widened by 8m through building 550m of new river walls. The bridge also protects the tunnel dug to lay power lines.

The southern roof support, which is 9m high, 28m long and over 5m wide, has been constructed using 850m³ of concrete. The north-east roof support has a steel frame in place with 4m of concrete.

Most of the foundations have already been built by sinking around 1,000 concrete piles 25m into the ground. The pools have been excavated.

Land reclamation

Eleven commercial buildings have been demolished from the 55,000m² site to facilitate the construction of the aquatic centre. The site was originally contaminated with petrol, oil, tar, solvents and heavy metals such as arsenic and lead. Around 140,000t soil was transported from other areas of the Olympic Park to fill the site.



Expand Image Expand Image
The London Aquatic Centre was designed by Pritzker Prize-winning architect Zaha Hadid.



Expand Image Expand Image
An aerial view of the London Aquatic Centre, which is currently in construction.



Expand Image Expand Image
An artist's impression of how the London Aquatic Centre will look inside during the Olympic Games.



Expand Image Expand Image
An artist's impression of how the centre will look in legacy.



Expand Image Expand Image
A CGI representation of the aquatic centre after the Olympic Games.



Expand Image Expand Image
A digital impression of the framework of the aquatic centre roof; the roof weighs 2,800t and is already being acclaimed as a sculptural masterpiece.



Expand Image Expand Image
An artist's impression of how the aquatic centre will look during the Olympics.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  

Suppliers
Grace Construction Products

Newsletter Sign-Up
For all the latest news in the design and construction industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Projects
Features
Inside Architecture
Speakers' Corner
White Papers
Jobs & Careers
Gallery
News & Updates
Events Listings
Newsletter Archive
Newsletter Sign-Up
Advertise
About Our Services
Client Area


RSS What is RSS
For everyone in building design and construction