Beijing National Stadium, China

Email-Icon
 
Print-Icon
 
Link-to-us
key facts
Key Data
Budget
£280m
Construction Time
3 years
Capacity
91,000 for Olympics, reduced to 80,000 afterwards
Height
69.2m above level pitch level
Size
3 million cubic metres
Completion
2008 ready for Olympics
Architects
Herzog & De Meuron Architekten, China Architecture Design & Research Group

The £280m Beijing National Stadium is set to be a stunning landmark building for the staging of the 2008 Olympic Games (opening on 8 August and closing on 24 August 2008).

The innovative structure was designed by Herzog & De Meuron Architekten, Arup Sport and the China Architecture Design & Research Group, and has been nicknamed the 'Bird's Nest' due to the web of twisting steel sections that form the roof.

"The £280m Beijing National Stadium is set to be a stunning landmark building for the 2008 Olympic Games."

As well as creating a modern stadium, the team was challenged with creating a venue that was part of the culture of China and that would put Beijing on the map.

The 91,000-seat stadium was designed to incorporate elements of Chinese art and culture; one of the design team is a Chinese artist. When the Olympics are finished the seating capacity will be reduced to 80,000. The stadium is 333m long from north to south, 294m wide from east to west, and 69.2m tall.

WORK PROGRESS

Construction work began on the stadium with earthworks and foundations in late 2003 and the main construction work started in March 2004. By August 2004 construction work had been halted due to the perceived high construction costs. The designers were asked to change the design to save money.

In the new design, the roof of the stadium was omitted completely. However, many experts believe this made the stadium safer from seismic activity. However the omission of the roof has significantly reduced construction costs. As a result of the design changes the total consumption of steel in the main structure has been reduced by 22.3% from the original design.

Also, because the hole in the top of the stadium is now enlarged, the total surface of its membrane structure has been reduced by 13%. The construction of the Olympic stadium resumed at the beginning of 2005; hence the adjustment from the original finishing date of 2006 to the start of 2008. The stadium was opened on 18 April 2008 (final work was completed in May 2008).

FINANCE

The China International Trust and Investment Corporation (CITIC) consortium, who raised 42% of the finance for the project in return for a 35-year tender after the Olympics are finished, comprises the CITIC Group, the Beijing Urban Construction Group, the Golden State Holding Group of the United States, and the CITIC Group affiliate Guoan Elstrong (a public, private partnership arrangement).

The remaining 58% is funded by the Beijing municipal government and this has been entrusted to the Beijing State-owned Assets Management Co Ltd as the city government's representative.

NATIONAL STADIUM DESIGN

As this is an Olympic venue, there are many standards that the team have to conform to. Everything from the width of the track to the size and location of the long and high jump pits needs to satisfy the requirements set out by the International Olympic Committee (IOC) and the International Amateur Athletics Federation (IAAF).

The stadium also had to be designed for the Paralympics, which takes place after the Games.

"Construction work began on the Beijing national stadium with earthworks and foundations in late 2003."

For this, the number of spaces for wheelchairs had to be increased considerably and put into various locations around the stadium, in both competitor and spectator areas.

The main requirements from the client, the National Stadium Company, which was established by the Beijing State-owned Assets Management Co Ltd, and the CITIC Consortium, were to create a bold, stand-out, world-class stadium, and to design in as much flexibility as possible for future use.

The stadium will host other sports such as football and events including concerts. One end of the stadium has amphitheatres that could be used to stage concerts once the grass is covered over.

As well as getting the inside of the stadium right, the concourses and space around the stadium also had to be carefully thought out for future use. The concourses are very wide to allow people plenty of space to access the refreshment and merchandising stalls. This is integrated with a large mixed-use retail development under the plinth of the stadium, with shops, restaurants, cinemas, a health club and parking.

The new stadium could be home to the Beijing GuoAn football club that plays in the Chinese Super League after the 2008 summer Olympics are over. This move though has yet to be confirmed by the football club.

CONTRACTORS AND CONSTRUCTION

Construction began on 23 December 2003 and was finished in early 2008. Beijing Mechanical Construction Company won the bid for earthwork and foundation treatment in November 2003 and work began almost immediately. CITIC Internationals Contracting Inc was the major construction contractor.

Structural engineering, mechanical and electrical engineering, fire safety engineering, acoustic design are the responsibility of Ove Arup & Partners. Beijing Urban Construction Group Co. Ltd (BUCG) is managing the project along with China Architecture Design & Research Group.

To minimise the formwork construction on the bowl, the design team have favoured the use of precast concrete. A terrace of L-shaped precast units spanning areas between the supporting reinforced concrete in situ beams will make up the section of the middle and upper tiers. The stadium will be supported by 24 main columns of 1,000t each, which is far more than the weight of those in a conventional stadium and spaced in what appears to be a random pattern (construction has required 42,000t of steel).

"As this is an Olympic venue, there are many standards that the team have to conform to."

NATIONAL STADIUM ARCHITECTURE

The team wanted to get an optimum balance between making sure every spectator had a good view, creating a good atmosphere and designing an elegant building. It also needed to be aware of the different uses of the stadium; for example, when used as an athletics stadium, the most important view is at the finish line of the running track but when used for football, the best views are at the centre line.

Getting everyone close enough in such a big venue was a real challenge and getting the calculations right was an immense task. For example, changing the height of the first row of seating by just 100mm would make the stadium significantly larger and higher and increase the cost by several million pounds.

To achieve the optimum design, the team relied heavily on parametric design software. This helped to work out the sightlines, the bowl geometry, airflow to keep the grass in good condition, seismic studies and to design the external envelope.

While the surface of the structure is simple, the geometry is complex – the calculations were so numerous and complicated that they could not be solved manually. Software was needed to make sure that the web of twisting steel sections fitted together, as they have to twist and bend to follow the surface accurately.

The main elements support each other and converge into a grid formation. The stand of the stadium is a seven-storey shear wall system with a concrete framework. The upper part of the stand and the stadium steel structure are actually separated from one another, but both of these are based on a joint foundation.

The roof is covered with a double-layer membrane structure, with a transparent ETFE (ethylene tetrafluoroethylene) membrane fixed on the upper part of the roofing structure and a translucent PTFE (polytetrafluoroethylene) membrane fixed on its lower part. A PTFE acoustic ceiling is also attached to the side walls of the inner ring.

The spaces in the structure of the stadium are to be filled with inflated ETFE cushions. On the façade, the inflated cushions are mounted on the inside of the structure where necessary, to provide wind protection.

"The Beijing national stadium roof is covered with a double-layer membrane structure, with a transparent ETFE."

Since all of the facilities – restaurants, suites, shops and restrooms – are all self-contained units, it is possible to do largely without a solid, enclosed facade. This allows natural ventilation of the stadium, which is the most important aspect of the stadium's sustainable design.

To keep costs down, all the structural elements of the stadium are contained within it, so there are no towers or cable nets. The bowl of the structure is split into eight zones, each with its own stability system, making each zone effectively its own building.

Entrance to the stadium will be controlled by tripod barriers supplied and fabricated by Kaba Gallenschütz of Germany. The project has involved the installation of 138 of these units at the 12 ingresses of the stadium.



Expand Image Expand Image
The 100,000-seat National Stadium in Beijing is a multi-use sports venue and will be ready for the 2008 Olympic Games.



Expand Image Expand Image
The stadium has a moving roof so that the environment can be controlled.



Expand Image Expand Image
The concourses are very wide to allow people plenty of space to move around, and for refreshments and merchandising stalls.



Expand Image Expand Image
To earthquake-proof the stadium, the bowl and roof were split into two separate elements and the bowl split into eight zones, each with its own stability system and effectively its own building.



Expand Image Expand Image
The steel structure of the stadium appears random but every element is carefully integrated.



Expand Image Expand Image
The Beijing National Stadium upon completion.



Expand Image Expand Image
The stadium is a fitting centrepiece for the Beijing Olympic Games.



Expand Image Expand Image
The Beijing Olympic Stadium lighting was chosen to produce a visual spectacle at night.



Expand Image Expand Image
The 'Birds Nest' alongside the Watercube.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Home
New On This Site
Products & Services
Company A-Z
Projects
Features
Inside Architecture
Speakers' Corner
White Papers
Jobs & Careers
News & Updates
Events Listings
Newsletter Archive
Newsletter Sign Up
Advertise
About Our Services
Client Area


RSS What is RSS
For everyone in building design and construction