Key Data:
Estimated Investment
£20m (total project cost), £16m (build cost)
Completion Date
September 2005
Key Players:
Architect
Capita Percy Thomas
Main Contractor
Birse Build Ltd
Structural Engineer
Buro Happold
Quantity Surveyor
Gardiner & Theobald