Here are the top five multi-family housing construction projects that commenced in the UK in Q2 2022, according to GlobalData’s construction projects database.

1. Clapham Park Regeneration: Phase II – $2,039m

The project involves the construction of a residential community comprising 2,400 multi-story homes ranging up to 14-story on 36ha of land in South London, Greater London, The UK.

Construction work started in Q2 2022 and is expected to be completed in Q4 2025.

The project aims to demolish 864 residential homes and 614m2 of non-residential floorspace to provide better residential facilities in the region. The project will be developed across 16 sites within the scheme.

2. Manor Road Quarter Mixed-use Community – $250m

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

The project involves the construction of a mixed-use development community in Canning Town, London Borough of Newham, England.

Construction work commenced in Q2 2022 and is expected to finish in Q4 2024.

The project site comprises Manor Road Retail Park and the former HSS site, and it’s close to the junction of Barking Road and the A13 Newham Way.

3. 1-4 Capital Interchange Way Mixed-Use Tower – $212m

The project involves the construction of three mixed-use towers ranging up to 16-story across 0.84ha of land in Brentford, West London.

Construction work started in Q2 2022 and is forecast to complete in Q3 2025.

The project aims to provide better housing and retail facilities in the region.

4. Pownall Street Mixed-Use Community – $200m

The project involves the construction of a mixed-use community comprising two buildings of nine and 16-stories in Liverpool.

Construction work commenced in Q2 2022 and is expected to be completed in Q4 2026.

The project will be located at the site bound by Park Lane, Pownall Street, Liver Street and Beckwick Street.

5. The Fairfax Residential Community – $186m

The project involves the construction of a residential community at Portugal Street East, Manchester, England, the UK

Construction work started in Q2 2022 and is expected to be completed in Q3 2024.

The project aims to provide residential facilities to the city of Manchester, and it is a part of the New Cross Development Framework.

Methodology:
This analysis is drawn from GlobalData’s global construction projects database, which tracks new construction projects over $25m from announcement to completion.